On the afternoon of October 28, the signal for the shutdown of BOG high-pressure compressor A came over the intercom, marking the successful 48-hour air load start-up of BOG high-pressure compressor A at the Wuhu LNG receiving station.
Employees are recording the compressor test pressure, temperature and other data in real time
The BOG high-pressure compressor is a key equipment in the BOG treatment process. When the receiving station is put into operation, the pressurized output of BOG will be realized through the compressor. Therefore, the continuous operation of the BOG high-pressure compressor for 48 hours without interruption has become an air load test before the project is put into production. critical step. In order to ensure the safe and stable operation of the equipment and ensure the complete success of the load start-up, the storage tank division formed a special work team and set up a test run team to plan various tasks in advance, scientifically organize shifts, and cooperate with participating units to further strengthen Equipment debugging, strengthening on-site safety management, and after 48 hours of hard work, the air load test of BOG high-pressure compressor A was finally completed on October 28.
In the next step, the Storage Tank Division will take the successful air load test start-up of BOG high-pressure compressor A unit as an opportunity to carefully sum up experience, strictly control project construction quality, strengthen on-site safety risk management and control, and go all out to lay a solid foundation for subsequent joint commissioning and production. Base.